Methodology and sources
Flush exists to make Irish public spending easier to check, not to tell you what to think about it. This page sets out where every number comes from, how derived figures are calculated, and the words we use — and avoid — to describe them.
Fact and analysis are kept apart
What a source states: a figure, a date, a status, or a reason the source itself gives — always with the source linked beside it.
Anything Flush adds by interpretation. Shown in a separate, labelled box and never mixed into a figure or headline.
Why we don't call it “waste”
A budget overrun is not automatically waste. Costs rise because scope is added, because prices change between an early estimate and a tender, because a figure is restated to include VAT or equipment, or because something went wrong. The number alone cannot tell these apart. We describe what the evidence establishes — a cost increase, a variance, a delay, documented expenditure — and leave the judgement to you. Where an audit or review has made a finding, we quote it and link it.
Terms
- Cost increase / budget variance
- The difference between two published cost figures for the same project. It says how much a figure changed, not why, and not whether anyone did anything wrong.
- Like-for-like
- Both figures cover the same scope (e.g. construction only) and the same price basis (e.g. 2025 prices, excluding VAT). Only then is the variance a measure of the same thing changing.
- Not like-for-like
- The figures differ in scope or price basis. We still show the difference, because it is what was published, but flag it beside the number and explain what differs.
- Documented expenditure
- An amount a source says was spent, where no original budget has been published for comparison. No variance is shown.
- Delayed project
- A project whose published completion or opening date has moved later. Delay is recorded as a date change, not as a cost.
- Contract value
- The value a public buyer entered on eTenders when publishing an award. It may be an estimate of total spend over the contract’s life, not money already paid.
- Allocation
- Money planned for a year in the published estimates. It is not the same as money paid out.
Calculations
- Variance = latest published figure − earlier published figure.
- Percentage variance = variance ÷ earlier figure × 100, rounded to a whole number. Not shown where the earlier figure is zero or unknown.
- Per resident = amount ÷ CSO population estimate (5,525,600, April 2026).
- Share of total = sector ÷ total × 100, one decimal place.
- The running counter on the homepage spreads the year's allocation evenly over the year. It is an illustration of scale and is labelled as one; real spending is uneven and is published monthly by the Department of Finance.
- No cross-project totals. We do not add variances from different projects together: they are measured in different years' prices and on different bases, so the sum would not mean anything a source could stand behind.
- Amounts are shown as published. Billions are given to two decimal places where the source does (e.g. €15.75bn) and are never rounded up.
Contract awards
- The data is what public buyers entered on eTenders. Flush does not correct it; if a value looks wrong, the buyer's entry is the place to check.
- Contract values are not summed, because one award can appear once per supplier with the same total on each line.
- County is derived only where the authority's own name contains a county (e.g. “Kerry County Council”).
- Category is the EU CPV division of the main CPV code where one is published, otherwise the category the buyer entered.
- Framework agreements themselves, and awards under €25,000, are not in this dataset.
Data sources, freshness and caching
whereyourmoneygoes.gov.ie (Dept of Public Expenditure)
- What
- Total expenditure and expenditure by sector
- How obtained
- Read daily by an automated job; a capture is only used if its sectors add up to the published total (±1%). Cached in our database.
- Source updates
- Changes on Budget day and when estimates are revised
- Current status
- 2026 figures, read 1 Mar 2026
Office of Government Procurement — eTenders award CSVs (data.gov.ie)
- What
- Contract awards over €25,000: authority, supplier, value, date, category, reference
- How obtained
- Found through the data.gov.ie API and imported automatically, newest release first. Rows are de-duplicated on the award’s own fields.
- Source updates
- Quarterly
- Current status
- Not yet imported
- What
- Population, for per-resident figures
- How obtained
- Entered by hand from the CSO release and checked on each annual release.
- Source updates
- Annual (August)
- Current status
- 5,525,600 (April 2026)
- What
- Published estimates and outturns for individual projects
- How obtained
- Entered by hand, each with its own source and date, and re-checked on the date shown on each project page. Official documents are preferred; where only a news report of an official statement could be linked, the source list says so.
- Source updates
- When a new figure is published
- Current status
- See each project page
Every document cited
- Where Your Money Goes — 2026 total expenditure by sectorDepartment of Public Expenditure, Infrastructure, Public Service Reform and Digitalisation · Jan 2026 · Official publication
- Population and Migration Estimates, April 2026 — Key FindingsCentral Statistics Office · 24 Aug 2026 · Official publication
- Contracts for Mini-Competitions and Standalone Awards (quarterly CSV)Office of Government Procurement, via data.gov.ie · quarterly · Official publication
- Contract awards for standalone and mini competitionsOffice of Government Procurement · quarterly · Official publication
- eTenders — Contracts for Mini-Competitions and Standalone AwardseTenders (Office of Government Procurement) · ongoing · Official publication
- PwC review finds "series of weaknesses" in planning and execution of National Children's HospitalTheJournal.ie (reporting the PwC review published by the Department of Health) · Apr 2019 · News report of official figures
- Children's hospital report says final cost will exceed €1.73bnThe Irish Times · Apr 2019 · News report of official figures
- National Children's Hospital cost has risen to more than €2.2bn, Donnelly confirmsThe Irish Times · 13 Feb 2024 · News report of official figures
- NCH to cost roughly €2.24bn, will open in 2026 — ministerRTÉ News · 19 Feb 2025 · News report of official figures
- June 2026 before new children's hospital treats patients (Public Accounts Committee)RTÉ News · 22 May 2025 · News report of official figures
- NCH opening could be delayed to autumn 2027, committee hearsRTÉ News · 25 Mar 2026 · News report of official figures
- Government approves MetroLink to proceed to detailed tender stageNational Transport Authority · 16 Sep 2026 · Official publication
- Cost of MetroLink project could rise as high as €17.5bnRTÉ News · 16 Sep 2026 · News report of official figures
- Dublin MetroLink cleared for tender at €15.75bn, 47% above 2022 estimateRailway Supply (reporting the Detailed Business Case review) · Sep 2026 · News report of official figures
- Estimate puts planned MetroLink costs at over €9.5bnRTÉ News · 4 Jul 2022 · News report of official figures
- MetroLink: the decades-long journey towards Ireland's first underground rail serviceThe Irish Times · 27 Jul 2026 · News report of official figures
- National Broadband PlanDepartment of Culture, Communications and Sport · ongoing · Official publication
- National Broadband Plan — State Aid ReportingGovernment of Ireland · ongoing · Official publication
- Is there still a need for a €2.9bn State intervention in the National Broadband Plan?The Irish Times · 23 Aug 2022 · News report of official figures
- What is the national broadband plan and what will it cost?The Irish Times · May 2019 · News report of official figures
- Dáil given report on PPARS systemRTÉ News · 13 Dec 2005 · News report of official figures
- PPARS became "money pit"Irish Examiner · 2005 · News report of official figures
- E-voting machines to be disposed ofThe Irish Times · Apr 2010 · News report of official figures
- Full review sought into €336k Leinster House bike shelterRTÉ News · 3 Sep 2024 · News report of official figures
- Group that runs Leinster House campus rejected alternative "cost effective" option for €336,000 bike shelter — reportThe Irish Times · 25 Sep 2024 · News report of official figures
- OPW minister welcomes bike shelter report findingsRTÉ News · 16 May 2025 · News report of official figures
Corrections