National Children's Hospital

Department / body
Department of Health
Delivery
National Paediatric Hospital Development Board
Status
Delayed
Location
Dublin

In March 2026 an Oireachtas committee heard that opening could be delayed to autumn 2027. Source: RTÉ News, 25 Mar 2026 (opens in a new tab)

A new national paediatric hospital at St James's campus, Dublin 8. Its published cost has been revised several times since the Government investment decision in 2017.

The numbers

Documented fact

2017 Government decision → latest total (Feb 2025)

Earlier figure
€983m
Apr 2017
Latest figure
€2.24bn
19 Feb 2025
Documented variance
+€1.26bn / +128%
Not like-for-like

The 2017 figure covered construction; the latest figure also includes equipping, ICT and commissioning. Part of the difference is scope, not price.

Calculation

Variance = €2.24bn − €983m = €1.26bn

Percentage = €1.26bn ÷ €983m × 100 = 128%

Earlier: Construction. Latest: Total project, including commissioning.

Published cost figures, in order

Every published cost figure for National Children's Hospital
DateFigureAmountScope / basisSource
Apr 2017Government investment decision€983mConstructionSource: TheJournal.ie, Apr 2019 (opens in a new tab); The Irish Times, Apr 2019 (opens in a new tab)
Dec 2018Revised construction estimate€1.43bnConstructionSource: TheJournal.ie, Apr 2019 (opens in a new tab); The Irish Times, Apr 2019 (opens in a new tab)
Dec 2018Revised total including equipping and ICT€1.73bnConstruction + equipping + ICTSource: The Irish Times, Apr 2019 (opens in a new tab)
19 Feb 2025Latest total stated by the Minister for Health€2.24bnTotal project, including commissioningSource: RTÉ News, 19 Feb 2025 (opens in a new tab); The Irish Times, 13 Feb 2024 (opens in a new tab)

Other comparisons

Construction only: 2017 decision → Dec 2018 revision

Earlier figure
€983m
Apr 2017
Latest figure
€1.43bn
Dec 2018
Documented variance
+€450m / +46%
Like-for-like

What the sources say

Documented fact
  • The contractor, BAM, had lodged claims of €853m, of which €48m had been approved, according to evidence given to the Public Accounts Committee in May 2025. These claims are not included in the €2.24bn figure. Source: RTÉ News, 22 May 2025 (opens in a new tab)
  • Reason given by sourceThe PwC review (2019) found the project "was driven by an imperative for timely completion, within a cost envelope that was never adequate to deliver the envisaged outcome and from a design that was continually evolving." Source: TheJournal.ie, Apr 2019 (opens in a new tab)

Key dates

Government investment decision
Apr 2017
Expected opening (Feb 2025)
2026
Possible opening (Mar 2026)
Autumn 2027

Sources

Figures last checked against these sources on 1 Oct 2026. Where a news report is linked, it is reporting an official statement or document.

Spotted an error or a newer figure? Send us the source and we will correct it.