MetroLink

Department / body
Department of Transport
Delivery
Transport Infrastructure Ireland / National Transport Authority
Status
Approved to tender
Location
Dublin

On 16 September 2026 the Government approved MetroLink to proceed to the detailed tender stage. Source: National Transport Authority, 16 Sep 2026 (opens in a new tab)

A planned metro line from Swords to Charlemont via Dublin Airport and the city centre. Cost estimates have been published at each approval stage.

The numbers

Documented fact

2022 approved estimate (restated, 2025 prices) → 2026 estimate

Earlier figure
€10.7bn
Jul 2022
Latest figure
€15.75bn
16 Sep 2026
Documented variance
+€5.05bn / +47%
Like-for-like

Calculation

Variance = €15.75bn − €10.7bn = €5.05bn

Percentage = €5.05bn ÷ €10.7bn × 100 = 47%

Earlier: 2025 prices. Latest: Incl. contingency and inflation, excl. VAT.

Published cost figures, in order

Every published cost figure for MetroLink
DateFigureAmountScope / basisSource
Mar 2018First published estimate (preferred route)€3bnEarly estimate; scope and price basis not comparable with later figuresSource: The Irish Times, 27 Jul 2026 (opens in a new tab)
Jul 2022Preliminary Business Case — Government Approval Gate 1€9.5bnrange €7.16bn–€12.25bn2021 pricesSource: RTÉ News, 4 Jul 2022 (opens in a new tab); Railway Supply, Sep 2026 (opens in a new tab)
Jul 20222022 central estimate restated by the NTA in 2025 prices€10.7bn2025 pricesSource: Railway Supply, Sep 2026 (opens in a new tab)
16 Sep 2026Detailed Business Case — approval to tender€15.75bnrange €14.44bn–€17.49bnIncl. contingency and inflation, excl. VATSource: National Transport Authority, 16 Sep 2026 (opens in a new tab); RTÉ News, 16 Sep 2026 (opens in a new tab)

Other comparisons

2022 estimate as published → 2026 estimate

Earlier figure
€9.5bn
Jul 2022
Latest figure
€15.75bn
16 Sep 2026
Documented variance
+€6.25bn / +66%
Not like-for-like

Different price bases (2021 vs current); the like-for-like comparison above adjusts for this.

2018 first estimate → 2026 estimate

Earlier figure
€3bn
Mar 2018
Latest figure
€15.75bn
16 Sep 2026
Documented variance
+€12.75bn / +425%
Not like-for-like

The 2018 figure was an early estimate on a different scope and price basis.

What the sources say

Documented fact

Key dates

Preferred route published
Mar 2018
Approval Gate 1 (Preliminary Business Case)
Jul 2022
Approval to tender (Detailed Business Case)
16 Sep 2026

Sources

Figures last checked against these sources on 1 Oct 2026. Where a news report is linked, it is reporting an official statement or document.

Spotted an error or a newer figure? Send us the source and we will correct it.